Eustis, Fla. (November 28, 2018) Built Rite crews have moved into the final phase of the project.  The milling of Lakeview Avenue is completed and crews are currently installing new sanitary sewer from West Crooked Lake Place to approximately 200 foot east of Townhill Drive.

Public-works-logo

Unfortunately, storm sewer installation on the north side of Lakeview Avenue has come to a halt due to conflicts with the old sanitary sewer system.  Once the new sanitary sewer is installed, past Townhill Drive and FDEP approval is obtained, the old system can then be connected to the new system. 

As the storm system is installed, crews will follow replacing road base, limerock, curbing and sidewalk. Portions of Lakeview will closed as the crews move east.  If you need assistance or directions navigating the detours, the on-site crews can help you get through.

All trash and garbage schedules will remain the same. Please place your trash and garbage to the roadside on your normal days. We thank you for your patience during this project.